Project Details
-

Project Name
ÇÖPLER SULPHIDE EXPANSION PROJECT
-

Client
Anagold | Wood (Former Amec FW) | GAP IPMT
-

Project Duration
Commencement :
Completion :
-

Location
İliç Erzincan, Turkey
Scope
Project Site Northern Area Steel/ Mechanical/ Pipe Installation
• Nine 398.00-tonne process tanks, 3 thickeners (445.00 t)
• 3,133.00 tonnes of steel
• 4,374.00 tonnes of mechanical equipment
• 116.939 WDI process pipe (CS/SS/TI/HDPE)
Tailing Storage Facilities Pipeline
• Between 17.04 km Ø 100 ~ Ø 500 diameter
Raw water pipeline
• Between 2.60 km Ø 100 ~ Ø 500 diameter
Finishing works of process buildings (21 pieces)
• 12,671.00 m2